Posted on: August 26, 2018

Message from National Grid regarding gas main work in the area of Columbia St. to Johnston Ave.

Below is the location overview of the projected gas main and service replacement work that began the week of 7/30/18.  This work will be performed by one of National Grid's contractors.


1. Install 465' of 6" plastic gas main on Chestnut St (Columbia St-Younglove Ave)

2. Install 675' of 2" plastic gas main on Grant St (Younglove -End)

3. Install 1410' of 2" plastic gas main on Broadway (Younglove -Garner)

4. Install  950' of 2" plastic gas main on McElwain Ave (Walnut-End)

5. Install  545' of 2" plastic gas main on Oak St (McElwain - Johnston)

We will also be upgrading the low pressure existing plastic gas mains on the following:

1. McElwain Ave (Between houses 2-16)

2. Chestnut St (Younglove - End)

3. Johnston Ave (Chestnut-Broadway)


Updates will be provided as soon as they become available from National Grid. 